Case Study: Building a State-of-the-Art Nanotechnology Center By: Eric Torkildson October 2004
A2C2 --
Cornell University
in Ithaca, New York, houses the countryís oldest federally
sponsored nanotechnology centeróthe Cornell Nanoscale Science
and Technology Facility (CNSTF). The center, which was built more
than 20 years ago, had outgrown its existing faciŒities in
the campusí Knight Laboratory. To provide a new state-of-the-art
nanotechnology research and teaching facility for the CNSTF, Cornell
turned to McCarthy Building Companies, Inc. and Welliver McGuire.
As a national center, the CNSTF needed to attract visiting
researchers from other universities and industries. Therefore,
the new $50 million Duffield Hall had to be one of the countryís
most sophisticated research and teaching facilities for nanotechnology.
This included the need to feature four types of labs: cleanroom,
wet, dry, and specialty labs; including a 20,000-square-foot
cleanroom with a teaching laboratory for training students in
nanotechnology processes.
In addition, the project required that the existing CNSTF
in Knight Laboratory be fully operational with very limited disruptions
during construction of Duffield Hallóa daunting task considering
how disruptive even minor vibrations are to a nanotechnology
lab.
Challenges and Solutions
Construction Vibrations
While being produced, nano objects must be motionless within
nanometers (one billionth of a meter, about 3-4 atoms wide) and
need extremely stable environments with vibration rigorously
controlled. This was especially challenging because the construction
of Duffield Hall, including blasting through rock for foundation
prep work, was taking place adjacent to the existing lab.
To ensure the blasting and other construction activities would
not interfere with CNSTF research, McCarthy/Welliver McGuire
met every week with more than 20 representatives from the CNSTF
operations staff to carefully schedule construction work. In
addition, the construction team installed vibration monitors
with such a high level of sensitivity that they can record a
door being shut in the adjacent building. The monitors tracked
vibration levels and sounded alarms if vibrations reached a certain
threshold that might have interfered with research work.
Vibrations in the New Building
In addition to construction vibrations interfering with the
existing CNSTF, the Contractor needed to build the new CNSTF
facility in a way that avoided vibrations that are typically
present in most buildings due to movements in internal systems
and factors in the external environment. The cleanroom and electron
microscopy suite in the new CNSTF require extremely stable environments
due to the sensitive nature of the equipmentóeven movement
from a passing truck could create vibrations that could affect
research. To diminish vibrations in the new facility, the construction
team constructed five isolated or ìfloatingî slabs,
which are separated from all building elements, preventing vibrations
caused by ground and internal building vibrations from carrying
through to the research areas.
Also, machinery in the facility that causes vibrationsófor
example, elevator and air conditioning systemsówas installed
away from the research areas.
Electromagnetic Fields
Duffield Hall houses the latest in electron microscope technology.
This sensitive microscope and other research equipment in the
cleanroom can be affected by stray electrical currents, which
are typically present in buildings. The Contractor took extra
steps during construction to eliminate possible stray electrical
currents in the new facility.
The construction team isolated the reinforcing steel rods of
the facility from each other and coated them with epoxy to eliminate
possible continuity. Isolation transformers were used to segregate
wiring throughout the facility to reduce any faint signals. Even
the ductwork was built in fiberglass rather than metal to reduce
electromagnetism.
Cleanroom Protocols
In a nanofabrication area, even a particle of dust can compromise
research, demonstrating the importance of maintaining an extremely
clean environment. To provide air that is free of dust, a complex
heating, ventilation, and air conditioning (HVAC) system was
installed. The HVAC system was built to circulate 10 to 20 times
the amount of air provided in a typical laboratory and forced
air through filters that trap most particles.
To achieve this clean environment, the contractor implemented
several levels of cleanroom protocols, starting during the early
stages of construction. By the end of the project, the construction
team was gowned in protective gear, used a specialized HEPA filter
vacuum system during certain procedures such as welding, and
thoroughly wiped down all construction tools and materials before
entering lab areas.
Cleanroom Tool Installation
This projectís most critical component was completing
the cleanroom finishes and installing its sensitive equipment.
To ensure the cleanroom had the latest, most state-of-the-art
equipment, the university and construction team held off on procuring
equipment until only a few months before it had to be installed,
resulting in a very tight timeline to prepare the equipment for
transport to the cleanroom.
The equipment transportation preparation process was a challenging
one due to stringent clean environment requirements which required
new lab equipment to be fabricated in a cleanroom or thoroughly
cleaned prior to being admitted into the new facility. The equipment
and all of Knight Laboratoryís cleanroom operations had
to be moved to Duffield Hall through a special temporary corridor
the construction team built to join the two facilities so that
equipment and research could be moved from one to the other without
ever leaving a clean environment.
Knight Lab Utilities
The project required the demolition of Knight Laboratory, a
building with a variety of intricate utilities running through
it, to make way for the new atrium. Several of the utilities
had to be rerouted to make way for the new construction. The
utility work was conducted as the project was nearing completion
and the end of its budget, requiring detailed preplanning from
the contractor to ensure costs were contained. For this planning
process, the construction team referenced old utility and shoring
drawings from the 1950s ñ 1970s to research the details
of the original building. From these references, assembled detailed
drawings were able to be made to understand the scope of the
utility work and provide subcontractors with a clear vision of
the work before it began in order to reduce surprises.
Harsh Winter Weather
Mother Nature also played a role in this projectís challenges.
Ithaca experienced unusually cold weather during key points in
the construction process. In late 2003, the area experienced
a two-month period without temperatures above freezing. During
that time, there also was three to four weeks where the temperature
did not rise above 10 degrees. This required the contractors
to work diligently to keep the exposed utility lines from the
demolished Knight Laboratory from freezing.
Conclusion
By forming a solid partnership and holding regular planning
meetings with Cornell University and CNSTF operations staff,
McCarthy/Welliver McGuire was able to anticipate challenges and
address them in a timely manner, therefore ensuring the highly
successful, on-budget and on-time completion of the $42 million
Duffield Hall project.
The project, which began in August 2001 and was completed in
July 2004, expanded Cornell Universityís nanotechnology
facilities by 153,000 square feet and will undoubtedly help to
maintain the universityís leadership on the cutting edge
of nanotechnology research and teaching. And, with the flexibility
the construction team built into the facility, Cornell University
will be nimble enough to respond quickly to future trends in
engineering researchóincluding being able to easily modify
and convert the lab spaces.
Cornell University was impressed with the construction teamís
ability to limit disruptions to the existing CNSTF, students
and staff while building at the busiest intersection on campus
and to stay on schedule despite various challenges.
ìMcCarthy and Welliver McGuire have done a tremendous
job in constructing Duffield Hall and especially the cleanroom,î said
Robert Stundtner, project director for science and technology
project management at Cornell University. ìThe team has
met every challenge of building a very sophisticated and sensitive
facility that will enhance nanoscale research and development
for years to come. In addition to building in the heart of the
Engineering College, McCarthy and Welliver McGuire have maintained
operations of the existing cleanroom, absorbed $5 million in
additional work, achieved an outstanding safety record and still
met our demanding schedule needs.î
Cornell University demonstrated how proud it is of the new facility
by hosting a ìPresidentís Round Tableî discussion
for Bill Gates (of Microsoft fame) in Duffield Hall in April
2004.